Working schedules are assigned to departments in the Departments menu (see Departments menu). If the working schedule is assigned to a department, then it is automatically assigned to all employees of the department.
To assign working schedule to a department, do the following:
- Go to the Departments menu.
In the Departments tree (1), select the department to which the working schedule is to be assigned.
Attention!
Sub-departments do not inherit parent work schedules. Therefore, if there are sub-departments, then for each of them it is also necessary to set their own work schedule.
- Click the Change working schedule button (2). As a result, the Working schedule for <Department name> window will open.
The next procedure of assigning the working schedule to department is equal to procedure of assigning the working schedule to employee (see Configuration of working schedules and work start/end dates).
This completes the process of configuring the department working schedule.