In order to create the schedule item do the following:
- Go to the Schedules tab.
- Click the New item in the schedule link.
- As a result the New item in the schedule form is displayed.
In the Time group (1) enter the instant approaching which the required reports will be generated automatically.
Info title Note. The selection of required reports will be performed when the tasks are created (see Setting up the automatically executed tasks section).
Info title Note. In order to set current time it is convenient to use button (2).
- If the reports should be generated regularly since the specified instant then in the Repeat group set the checkbox in the boxes of required generation period (3).
- As a result the tweaking form of strategy for repeating is displayed (4). The procedure of filling it in is clear.
- In order to save the schedule item click OK (5).
...