To create a schedule, complete the following steps:
- Go to Settings → Options (1) → Time schedulesSchedules (1-2).
In the List of Time Schedules, enter the name of the required schedule (3) and click
.- Set the time intervals for the schedule:
Enter the interval's start time in the From column with the help of the buttons accessible by left-clicking the appropriate cell twice (1).
Button
Action
Shift the interval start back by 1 hour
Shift the interval start back by 5 minutes
Shift the interval start ahead by 5 minutes
Shift the interval start ahead by 1 hour
- Enter the interval's end time in the To column with the help of the buttons accessible by left-clicking the appropriate cell twice (2).
- Select the days of the week to be included in the interval by selecting the appropriate check boxes (3).
Create the necessary number of intervals to be included in the schedule.
Info title Note To delete a time interval, click in the corresponding row.
A visual display of time intervals for each day of the week is provided on the time chart.
- Click the Apply button.
Creation of a schedule is now complete.
...