- Go to the Worktime tab (1) of the Access Manager interface window (For more information about connecting the Worktime subsystem, see Configuring the Worktime subsystem).
- Go to the Schemes menu (2).
- Right-click the empty space on the left side of the window to open the context menu.
- In the context menu, select New (3). The Scheme settings form will open.
- In the Name field (1), enter the name of the scheme.
- In the Description field (2), enter the description of the scheme.
- From the Scheme type drop-down list (3), select the type of a scheme you want to use. The scheme type determines the duration of the scheme in days (4). There are three types of scheme available:
- Weekly—the duration of the scheme is seven days.
- Sliding—the duration of the scheme is set manually.
- Monthly—the duration of the scheme is 31 days.
If you selected the Sliding scheme type, in the Duration field (4), enter the duration of the scheme in days.
- In the Start date field (5), set the start date of the work scheme by clicking the button and opening a calendar, or enter the start date manually in the DD.MM.YYYY format.
- Set the parameters for each day of the work scheme:
- For each scheme day in table (6) assign a work period by selecting it from the Work period drop-down list (7) or by using the
search button (8). When you click the button, the Period search window will open, where you can select a work period from the list (3) or search it by parameters:- In the Name field (1), enter the work period name to search by it. The search starts with the first character.
- In the ID field (2), enter the work period ID to search by it.
- If necessary, in the Description field (9), enter a description of the scheme day.
- For each scheme day in table (6) assign a work period by selecting it from the Work period drop-down list (7) or by using the
- Click the Save button to save all changes.
...
Overview