A shift schedule is created as follows:
- Go to the Shift work section of the ACS bar.
The information pane will show previously created shift schedules and the shift work schedule bar will open. Click the New button (1).
Note:
This action can also be performed using the information pane's context menu. Right-click on any point in the information pane to bring up the context menu and then select the New menu item.- In the Name field, enter the name of the shift schedule (2).
- Specify the shift's start date in the Shift start field in DD.MM.YYYY format (3).
- Check the Skip holidays box to ignore holidays (4).
In the Shift time spinbox, use the up/down buttons to enter the total number of days in the shift schedule, including days off (5).
Note:
The current shift day is displayed in the corresponding field (6).- Configure the shift schedule's workdays. For each day, do the following:
- In the Shift day column, enter the shift day's index number (7).
- In the Beginning column of the table, enter the workday's start time in HH:MM:SS format (8).
- In the Ending column of the table, enter the workday's end time in HH:MM:SS format (9).
- Click Save to save the shift schedule (10).
This completes the process of creating a shift schedule.